Playground Update March 2018

Playground Update Following the appointment of HAGS to supply and install the equipment, the following timetable is agreed: Manufacturing period: 12 weeks 29 January to 23 April 2018 Pre-start meeting: w/c 23 April Site set-up (Welfare, Storage and Herris Fencing) : w/c 30 April Installation: w/c 30 April to 21 May Install safety surfacing/reinstate area; second fix – swing seats: w/c 21 May Provisional Grand Opening: Sunday 27 May at 1pm March 2018