Playground Update
Following the appointment of HAGS to supply and install the equipment, the following timetable is agreed:
Manufacturing period: 12 weeks 29 January to 23 April 2018
Pre-start meeting: w/c 23 April
Site set-up (Welfare, Storage and Herris Fencing) : w/c 30 April
Installation: w/c 30 April to 21 May
Install safety surfacing/reinstate area; second fix – swing seats: w/c 21 May
Provisional Grand Opening: Sunday 27 May at 1pm
March 2018